REIVAX replaces aging Basler SSE static excitation system, re-using the existing cabinet
The project scope included:
- • Supply of a mounting plate for excitation controls
- • Supply of a mounting plate for power components
- • Supply of a door-mounted panel with a 15” HMI
- Commissioning and training
The run-of-the-river power plant was built for two turbines, 25 CFS and 50 CFS. The generator is started as a motor since there is no turbine flow control and once synchronized, the variable flow dictates the power output.